Project cost calculator

What is the delay costing your team?

Put a value on the time tied up in a stalled project or a recurring hold-up.

Start with this example, then enter your own figures. Estimate time that is genuinely lost or tied up by the delay.

1Your team
Currency

Use the same currency for every amount. No exchange conversion is applied.

2The delay
Time unit
How often does it happen?

How it is calculated

  1. 01

    Hourly salary cost = annual salary ÷ 2,080 working hours.

  2. 02

    A working day is 8 hours; a working week is 40 hours. The model uses 260 working days, 52 weeks or 12 months per year, without deducting leave.

  3. 03

    Cost = hourly salary cost × people affected × hours lost × occurrences. One-off delays use one occurrence; recurring delays cover a full year.

  4. 04

    Salary excludes employer contributions, overheads and any separate project costs. Only count hours affected by the delay, rather than all elapsed project time.